Thermo Systems Begins Commissioning of Rehabbed LM2500 Gas Turbine


The Thermo Systems team commenced commissioning of a rehabbed Stewart & Stevenson LM2500 gas turbine (pictured at left) at the Morris Energy Dartmouth Power Plant in Dartmouth, MA.  Thermo has been contracted by Morris Energy to design, build, and commission the redundant PLC and SCADA system which will integrate the LM2500 with the existing power generation turbines. 

The Dartmouth Power Plant is currently operating a 40MW GE Frame 6 gas turbine and a 30MW steam turbine fed by the main turbine’s heat recovery steam generator. The current turbine is operated as a peaker and will come on line when requested by the power grid to increase capacity during peak demand.  The expansion project consists of adding the Stewart and Stevenson LM2500 Gas Turbine which will also operate as a peaker and will add another 20MW of capacity to the plant. 

Thermo Systems has been tasked with designing and providing the Balance of Plant Control (BOPC) system for the expansion. The BOPC has been designed with redundant processors, redundant instrument power and redundant HMI to allow the plant to maintain operation in the event of a control system component failure.  Thermo Systems worked with Morris Energy and Concord Engineering Group to create a custom controls solution for the operation of the turbine and its ancillary systems.

This project is being led by Thermo Systems Control Systems Project Engineer Thomas Davis.  Tom is a graduate of Purdue University with extensive experience in the power and controls industry.
Click below to view details.
More News

link_arrow Q4 2011 – Thermo Systems Ships First Panels for Rare Earth Mining Project

link_arrow Q3 2011 – Thermo Systems Commences Pilot Plant Commissioning Effort

link_arrow Q2 2011 – Thermo Kicks Off Systems Integration Contract for 48MW CHP Plant in California

link_arrow Q2 2010 – Thermo Systems Completes ETS Installation in the Kingdom of Bahrain

link_arrow Q3 2009 – Thermo Systems Begins Commissioning of Rehabbed LM2500 Gas Turbine
space
Q2 2009 – Thermo Systems Begins Campus Cogeneration Automation Project for NYU
Q2 2008 – Thermo Systems Receives Bio-Pharmaceutical Critical HVAC Award
Q2 2007 – Thermo Systems Principals Present Paper at IDEA
Q1 2007 - Thermo Systems Receives Automation Design and Build Contracts for API
Q4 2006 - Thermo Wins District Energy Construction Contract in Philadelphia, PA
Q3 2006 - Thermo Systems Delivers ETS Automation Packages for Bahrain Financial Harbour
Q2 2006 - Princeton University Facilities Engineering and Thermo Systems Mark Energy Savings
Q3 2005 - Thermo Systems Acquires Voltec, Inc.

© 2012 THERMO SYSTEMS, LLC. ALL RIGHTS RESERVED PRIVACYlLEGAL